Results of Emission Monitoring

2016-11-14

402

#

Emission from 07.11.2016 to 14.11.2016

Emission MPE, %
long-lived nuclides 0.0033
Inert gases 0.155
Iodine 0.0009

Ionizing radiation background on the industrial site and adjacent area has not changed. Its level corresponds to normal operation of the units and does not exceed natural background values.
Information Centre of SE KhNPP
24.25 mln. kWh was generated on November 13

2016-11-14

401

#

On  November 14, 2016, Khmelnitsky 1 operates at capacity of 1010 MW. On the previous day, 24.25 mln. kW*h of electricity was generated by Khmelnitsky 1. 315.53 mln.kWh has been generated since the beginning of the month.

Khmelnitsky 2 has been in outage for 37 days.

Radiation situation on the site and adjacent areas has not changed, and remains at the level corresponding to normal operation of power units, and does not exceed natural background values.
Information Centre of SE KhNPP