On November 1, 2017, the 1st unit's power is 633 MW. Daily generation of electricity is 16.4 million kWh and 507.3 since the beginning of month.
The 2nd unit's power is 1007 MW. Daily generation of electricity is 24.3 million kWh and 158.1 since the beginning of month.
Ionizing radiation background on the industrial site and adjacent area has not changed. Its level corresponds to normal operation of the units and does not exceed natural background values.