Results of Emission Monitoring

2018-02-05

# 40

Emission from 29.01.2018 to 05.02.2018

Emission MPE, %
long-lived nuclides 0.0029
Inert gases 0.0691
Iodine 0.0008

Ionizing radiation background on the industrial site and adjacent area has not changed. Its level corresponds to normal operation of the units and does not exceed natural background values
Information Centre of SE KhNPP

Daily Information on Khmelnitsky NPP Operation

2018-02-05

# 39

On February 5, 2018, Khmelnitsky-1 has been in outage for 91 days. On November 7, 2017, Khmelnitsky-1 was disconnected from the grid for middle maintenance.

Khmelnitsky-2 operates at 1009 MW power. Over the past day, the power unit generated 24.27 million kWh of electricity, and 97.11 million kWh of electricity has been generated since the beginning of the month.

Radiation situation on the site and adjacent areas has not changed, and remains at the level corresponding to normal operation of power units, and does not exceed natural background values.
Information Centre of SE KhNPP