Today, on May 8, Khmelnitsky 1 has been in maintenance for 34 days.
On the 3rd of April at 3:02 p.m. Khmelnitsky 1 was disconnected from the grid due to the actuation of generator protection system.

Khmelnitsky 2 operates at power of 1008 MW. Over the previous day the power unit generated 24.15 mln. kW*hour of electricity, and electricity generated from the beginning of the month amounts to 168.46 mln. kW*hour.

Radiation environment at the site and on the adjacent regions has not been changed, and remains on the level pertinent to normal operation of power units, and does not exceed natural background values.