Радіаційний стан навколо Хмельницької АЕС

2019-11-05

# 402

Emission from 28.10.2019 to 04.11.2019

Emission MPE, %
long-lived nuclides 0.0045
Inert gases 0.0797
Iodine 0.0009

Ionizing radiation background on the industrial site and adjacent area has not changed. Its level corresponds to normal operation of the units and does not exceed natural background values
Інформаційний центр ВП ХАЕС

Daily Information on Khmelnitsky NPP Operation

2019-11-05

# 401

On November 5, Khmelnitsky 1 has been in middle overhaul for 346 days.

Khmelnitsky 2  has been in overhaul for 40 days. On September 27, Khmelnitsky 2 was disconnected from the grid at 00:13 am for the scheduled middle maintenance. The maintenance will last 52 days.

Ionizing radiation background on the industrial site and adjacent area has not changed. Its level corresponds to normal operation of the units and does not exceed natural background values.
Інформаційний центр ВП ХАЕС